Shedhorn 4

The Shedhorn area is getting upgraded to a high speed quad.

Moving the former Ramcharger High Speed Quad to the Shedhorn area will take ride times from around 12 minutes to close to 5.

October 19, 2018

Shedhorn Drive cabinets are installed.

Drive cabinets are responsible for all functions of the lift, including stop and safety controls. The communication lines have been installed on Shedhorn and contain more than 87 total miles of wiring on the lift.

September 18, 2018

Towers and other equipment have been flown into place on the Shedhorn lift.

September 6, 2018

The top terminal of Shedhorn 4 is nearly finished with the installation of the new exterior housing. Additionally, improvements to Cow Flats are coming along nicely.

August 31, 2018

The Shedhorn bottom terminal foundation is coming along well. The top terminal has been installed and is awaiting new exterior housing.